Drivers using FM 2524, also known as Austin Avenue, in Brownwood should prepare for overnight construction beginning early next week. TxDOT’s contractor will continue the roadway project by paving the outside lanes while traffic moves through the work area.

The overnight schedule is intended to account for extreme temperatures. Work is expected to begin around 8 p.m. and finish each morning around 9 a.m. The outside-lane paving should take two to three nights to complete the final layer of asphalt.

Inside-lane work will follow

Once the outside lanes are finished, construction will shift to the inside lanes. That portion of the project is expected to take two to three weeks, weather permitting.

The overall project is anticipated to be completed by the end of September. The source does not provide a specific start date for the overnight paving, so drivers should watch for work beginning early next week after the Aug. 29, 2026 announcement.

Expect delays during overnight commute

Motorists should expect possible delays from 8 p.m. to 9 a.m. while paving is underway. Drivers traveling through the FM 2524 and Austin Avenue work area are encouraged to allow extra time for their commute or choose an alternate route.

TxDOT also advises motorists to drive carefully, obey the speed limit and avoid distractions in the work zone. The agency’s safety guidance is intended to help protect both drivers and construction workers as the paving continues.